Muni Naughty List – January, 2020
The Muni
continues its downward spiral of lost money, lost time, and lost opportunities
to reduce our carbon footprint. We have now officially spent, and lost,
over 9 years (2011-2019) and $32 million. Oh, what we could have achieved
with that time and money that is now forever lost! Worse, we must now
wait for another two years to even get a chance to vote and perhaps finally
figure out what a bad idea the Muni has become. If Santa had a list of
the Naughty Boulder Muni Monopoly Failures it would be long and include the
following:
1. Separation costs that were originally estimated to be $10
million are now around $110 million.
2. Taking millions ($4.3 million) from the General fund with no
certainty of repayment from Muni profits.
3. Rate increase of 30% 18 months after “day-one” as revealed
by a cash flow analysis that had to be acquired by legal (CORA) action.
4. Outdated and inaccurate engineering and cost analysis as a
basis to form a Muni AND a court case because of that which ended the Paper
Muni.
5. Ignoring the fact that new renewables like the Rush Creek
Wind Farm have already increased the stranded costs, and a failure to even
include stranded costs in recent cost analysis. In just the last 2 months
the stranded costs were given a value of zero in the financial analysis, thus
making all the great financial projections corrupt. Stranded costs will
never be zero and is likely to be about $300 million.
6. Not including the costs of other department’s working on the
muni until forced to do so, and taking years to finally admit that these are
true muni costs in financial reports.
Some employees worked 60% to 100% of their time on the muni, but were
not billed to the muni.
7. The Muni schedule was supposed to be complete in 2017 but
may extend to 2029 just to pay stranded costs, while Xcel will be at 80%
renewables by 2030.
8. Failure to include about 120 to 300 million in Going Concern
costs as part of condemnation on the flimsy basis that it has never been done
before in Colorado even though it has occurred in Colorado and has occurred
nationally.
9. Original intent to take 5,700 Gunbarrel customers and
facilities outside of the city.
10. Ignoring 10 million
dollars and more in lost undergrounding.
11. Trying to claim that shared poles don’t decrease safety and
reliability, and thinking that Xcel could be forced to share poles when there
was no reason for them to do so.
12. Costly legal missteps at the district court level, and at
the FERC. Wasting 4 years.
13. Numerous costly missteps at the PUC.
14. Blaming all these missteps on the PUC rather than poor
Boulder leadership and legal decisions.
15. Failure to get a significant majority of voters to support
anything other than limitations on the Muni effort.
16. Rejecting the conversion of all street
lights to LED’s for some bizarre reason, when all the towns around us have
already accepted them.
17. Boulder’s early plans:
o Assumed No requirement to submit a
separation plan to the PUC
o Assumed Acquiring a 30-mile transmission
loop without FERC approval
o Assumed Forcing Xcel to serve its
customers over city-owned facilities
o Assumed Forcing Xcel to design, build
and test Boulder’s side of the system
o Assumed Forcing Xcel to finance
Boulder’s separation and be paid after completion
o Assumed Xcel would finance its own
expenses for Boulder’s municipalization
o Assumed that a third party would do the
work for Xcel
All of these assumptions were wrong.
18. Boulder still assumes it can get all
costs estimated by 2020 but it never will. Costly court cases will drag
this out to at least 2021.
19. April 2017 - City Council rejected putting Xcel’s settlement
offers on the ballot thus DE-democratizing the Muni by preventing a vote on:
a.
Partnership
settlement to help Boulder achieve its environmental goals. OR
b.
A
Negotiated Buy-out Process in which Boulder would acquire the Boulder electric
distribution system. Xcel estimated the buy-out at $550-$750 million.
Boulder estimated the cost up to $900 million just to reject this option.
Boulder conducted a bad faith negotiation.
20. June 2018 - the Colorado Supreme Court
ruled to preserve Xcel’s right to challenge Boulder’s compliance with its own
Muni creation criteria, thus ending the paper muni.
21. Boulder continues to collect over 8
million dollars in carbon taxes that are not used for carbon reduction and apparently,
we see no contradiction in this illogical position.
22. So now we are stuck with no vote or
exit ramp on a Muni for 2 years thus highlighting the De-democratization of the
Muni Monopoly.
23. There is no item in the Muni Project schedule
for dealing with the FERC Stranded Cost issue.
The ridiculous Boulder response regarding this indicates the FERC
process is part of two other process that are scheduled to be complete by
December 2019. This is ludicrous.
24. October 2019 - The Condemnation process
has only been partially approved and facilities INSIDE substations still need
to be resolved. This will either add to
the condemnation costs, or the separation costs. This will add to the True Costs.
This
is the Muni Past, Present, and Future. Boulder fiddles while the planet
burns and floods.
Solar
incentives, wind incentives and a renewable energy certificates (REC’s) broker
would actually democratize, decentralize and decarbonize Boulder’s electric
supply. The Muni has failed us on all of these. Xcel is not the
problem. The Muni is the problem, and is the only thing standing between
us and our climate goals. Xcel hate is not getting it done. Lack of true
self-critical review is hurting us. Let’s end this growing naughty list.
More
details at: http://tinyurl.com/BoulderMuni
Support the
End the Muni Effort and donate at EndTheMuni.org
Patrick Murphy November 19,
2019
Lies and omissions.
Boulder doesn’t lie, it omits. Omits the
truth, the full truth.
The long and growing Muni Naughty List
documents that fact. You now each have a copy of the Growing Muni Naughty List
and it’s now in the record. You’ll need
to explain your position, not just now, but in the distant future. The Muni has not been wise, truthful, or
successful at any step along the way. We
have paid for, and lost, nine years of steps.
The inability to critically review the
Muni is not a sign of intelligence. You
have not critically and publicly reviewed the Muni or honestly evaluated the
alternatives. When I asked the previous mayor,
what is plan B if the muni fails. The mayor answered that there was a plan B, C
and D. Please tell us what those plans
are so we can fully evaluate what might be faster, cheaper, better and smarter
than the muni. Plan B, C, or D may actually work and not take until 2021 to
find out that the Muni debt would be laughable and insane.
What ever happened to “We are in a hurry
to reduce carbon”.
What ever happened to “The Muni will be
up and running by 2017”.
What ever happened to “local control”
when we are forced to give up control for two years to financially evaluate a
ten-year-old muni.
What ever happened to “The Muni
financials are sound and robust” but some of the high costs are treated as
zero.
Who starts a business and treats some of
the larger costs as zero and expects to be taken seriously? Boulder does, that’s who.
True Total
Cost
$753,898,854
With bond
costs, the total will be well over $1 BILLION.